Steel Activity Bulletin

Posted by Pam Beaudoin on 10/25/2019 2:35:00 PM

Memorial Building Project  - Steel Activity Bulletin

What to Expect From 10/28/2019 to 12/06/2019

During this phase of the project, the construction team will be working extended hours from 7:00 am – 6:00 pmto complete steel close to school.  It is anticipated that there will be a need for Saturday work during this period.

In addition to extended work days, this will be a period during which there will be an increase in the number of deliveries to the site.

  • Deliveries will be Monday – Friday from 10/28/2019 to 11/08/2019.
  • Crane Mobilization and first steel deliveries (2-3 trucks expected daily).
  • Police details have been scheduled, and they will be overseeing traffic pattern changes, including reversing the direction on Union Street periodically. MPD will be providing notices to neighbors impacted by parking bans during the hours of anticipated oversized load traffic

Memorial Building Project  - Steel Activity Bulletin

Memorial Building Project  - Steel Delivery Traffic Plan