This option of putting all students at Memorial School was considered as part of the MSBA feasibility process, but it was eliminated early due to a combination of regional, site, and practical constraints.
First, B1.1 this option would require an addition to the recently constructed Memorial Elementary School. Under the District’s regional agreement, we are required to maintain an elementary school in each member town. Advancing this option would raise significant questions about how that requirement would be met, while also concentrating a major investment at a single site.
Second, the option presented significant site challenges. The Manchester site is already constrained, and this approach would effectively overbuild the site, raising concerns about layout, functionality, and long-term usability. There are also environmental restrictions that limit how the site can be developed. In addition, existing features—such as the tennis courts—would need to be relocated to a new, yet-to-be-identified location, adding further complexity, cost, and uncertainty.
Third, this option would require altering a recently completed MSBA-funded project. That raises the potential need to repay previously awarded MSBA grant funding, and not all aspects of a new addition would necessarily be eligible for future MSBA reimbursement. This creates financial risk and makes the project less competitive within the MSBA process.
Fourth, there are timing and construction impacts. The evaluation matrix shows a longer projected construction duration—approximately 40 months, compared to 36 months for the preferred option—along with the added complexity of building onto an active school site.
This would likely increase disruption for students and staff and introduce additional project risk.
Finally, this option did not perform as well across several key categories in the evaluation matrix, including its ability to fully meet the educational program, support future growth, and provide a complete, long-term solution.
Taken together, this option introduced added complexity—from regional agreement considerations to site constraints and funding risks—while also scoring lower on the factors most important to the District. For those reasons, it was not advanced for further development.