Project Updates

  • October 2020

Please be advised that our second round of steel delivery to The Manchester Memorial Elementary construction project will occur from 10/13-10/20.  Deliveries will be between the hours of 7-7:30am, and 8:30 am-2:30 pm.  The Manchester Police Department has been notified and is aware of the deliveries and will be providing detailing services.  Please see attached our trucking route traffic and logistics plan for reference.

 

Also please be advised that the construction team will be working Sunday, 10/18, from 8:00 am-4:00 pm. This is rare for us – in fact, our first time working on a Sunday for this project.  We are pushing to get this next phase enclosed before cold weather settles in.   The operations will not produce significant noise and will be mostly steel framing detailing/welding.  The work will not include any heavy machinery, i.e. cranes, etc. 

 

  • November 2019

As of the October Construction Report, the Memorial School project is proceeding on time and on budget.  The steel is going up quickly, and the WT Rich Construction Team is on target to have it wrapped and ready for winter work by mid-December.

 

Here's the latest ariel view of the progress. 

 

  • October 2019

Memorial Building Project  - Steel Activity Bulletin

What to Expect From 10/28/2019 to 12/06/2019

During this phase of the project, the construction team will be working extended hours from 7:00 am – 6:00 pmto complete steel close to school.  It is anticipated that there will be a need for Saturday work during this period.

In addition to extended work days, this will be a period during which there will be an increase in the number of deliveries to the site.

  • Deliveries will be Monday – Friday from 10/28/2019 to 11/08/2019.
  • Crane Mobilization and first steel deliveries (2-3 trucks expected daily).
  • Police details have been scheduled, and they will be overseeing traffic pattern changes, including reversing the direction on Union Street periodically. MPD will be providing notices to neighbors impacted by parking bans during the hours of anticipated oversized load traffic

Memorial Building Project  - Steel Activity Bulletin

Memorial Building Project  - Steel Delivery Traffic Plan

  • October 2019

Memorial Building Project Ariel View!

Construction is underway at the Memorial School and we are on track to be in the new academic wing at the start of the 2020-2021 school year. 
 
Check out an ariel view of the progress.