Welcome to the website for the Manchester Essex Regional School District
District Seal
District Seal

Spacer
Site  This Folder
 

School Building Project - Schedule Summary

School Building Project - Schedule Summary *

Town Meeting Votes
February 2006



Design Phase  

 
       Schematic Design
Completed June 2006
       Design Development
Completed September 2006
       General Contractor prequalification
To be completed March 2007
       Complete Construction Plans and Specs
March 2007
       Permits
March 2007



Bid Phase  

 
       Issue plans and specs for bid
March 15, 2007
       Receive and open bids
April 25, 2007
       Select Contractor
May 1, 2007
       Award construction contracts
May 14, 2007



Construction Phase

Lincoln Street (Middle School / High School) Site  

 
       Mobilize
April - June 2007
       Start construction (on existing football field)
Late June 2007
       Complete new High School / Middle School
May 2009
       Move into new building
Late June / July 2009
       Demolish existing school building
Late July 2009
       Start construction of new athletic field
August 2009
       Complete new athletic field and sitework
November 2009



Brook Street (“Coach Ed”) Site  

 
       Start construction (subject to approval):
April 2007
       Complete new athletic field and sitework
August 2007



* Note: all dates are approximate, and are subject to change.