School Building Project - Schedule Summary *
Town Meeting Votes |
February 2006 |
Design Phase
Schematic Design |
Completed June 2006 |
Design Development |
Completed September 2006 |
General Contractor prequalification |
To be completed March 2007 |
Complete Construction Plans and Specs |
March 2007 |
Permits |
March 2007 |
Bid Phase
Issue plans and specs for bid |
March 15, 2007 |
Receive and open bids |
April 25, 2007 |
Select Contractor |
May 1, 2007 |
Award construction contracts |
May 14, 2007 |
Construction Phase
Lincoln Street (Middle School / High School) Site
Mobilize |
April - June 2007 |
Start construction (on existing football field) |
Late June 2007 |
Complete new High School / Middle School |
May 2009 |
Move into new building |
Late June / July 2009 |
Demolish existing school building |
Late July 2009 |
Start construction of new athletic field |
August 2009 |
Complete new athletic field and sitework |
November 2009 |
Brook Street (“Coach Ed”) Site
Start construction (subject to approval): |
April 2007 |
Complete new athletic field and sitework |
August 2007 |
* Note: all dates are approximate, and are subject to change. |